DAR MEMORANDUM CIRCULAR NO. 12-03

 

TO                :     All Regional Directors, All Provincial Agrarian Reform Officers, All Municipal
                            Agrarian Reform Officers and All Others Concerned

SUBJECT    :     Dissemination of LBP Land Valuation Guideline No. 97-004 and 97-005, Series
                            of 1997, Entitled "Valuation of Roads and Bridges"

 

The attached LBP Land Valuation Guideline Nos. 97-004 and 97-005, Series of 1997 entitled, "Valuation of Roads and Bridges" are hereby disseminated to inform DAR field offices regarding the policy on the valuation of roads and bridges as improvements in lands covered by the Comprehensive Agrarian Reform Program (CARP).    DEcSaI

These LBP guidelines cover the valuation of roads and bridges as delineated in the Approved Subdivision/Segregation Survey Plan (ASP) and introduced by the landowner. Likewise, these stipulate the computation of the values of roads and bridges depending on their classification or condition.

Please be guided accordingly.

Diliman, Quezon City, August 12, 2003.

(SGD.) ROBERTO M. PAGDANGANAN

Secretary

 

July 2, 1997

LAND VALUATION GUIDELINE NO. 97-004

Series of 1997

 

SUBJECT:         VALUATION OF ROADS AND BRIDGES

 

In accordance with item II.E of DAR Administrative Order (AO) No. 6, Series of 1992, as amended by DAR AO No. 11, Series of 1994, valuation of improvements (non-crop) shall be undertaken by Land Bank. Further, Item No. 12 of A.O. No. 11 provides that the landowner shall not be compensated or paid for improvements introduced by the Government, farmer-beneficiaries or other third parties.

Buildings, machinery and equipment and other land improvements are valued using the "Cost Approach", with due consideration given to the current market prices of materials and labor for the construction of the aforesaid improvements and allowance for depreciation.    aDcTHE

I.          COVERAGE

This Guideline is hereby issued to address specifically the valuation of roads and bridges, as delineated in the Approved Subdivision/Segregation Survey Plan (ASP).

II.        DEFINITION OF TERMS

1.         Public road — shall refer to a passageway or easement, whether classified as national or local, that traverses the estate/plantation and links it to the adjoining towns or cities. This road usually serves as an access for transporting commerce, people and farm products.

2.         Plantation road — shall refer to a passageway (primary or secondary feeder road) that connects the remote areas of the estate with its main production center. This usually serves as an access for transporting agricultural inputs/outputs to or from the various production sites within the plantation.

3.         Bridges — shall refer to a structure built over a waterway (such as streams, creeks, brooks, canals, etc.), wide gully, etc. which may be made of either wood, concrete and/or steel, to provide a way across for vehicles or pedestrians.

III.       VALUATION PROCEDURES

Plantation roads and bridges introduced by the Government.

Roads and bridges constructed by the national or local government on landholdings acquired through expropriation or on lands donated by the landowner to the Government, whether or not segregated from the owner's title, are not eligible for coverage/acquisition.

Plantation roads and bridges introduced by the Land Owner (LO).

Roads and bridges originally constructed by the landowner, although considered as "public" passageways because of permanent and continuous use by vehicles or pedestrians, shall be compensated, provided that there are no documents to show that said passageway has been expropriated by the Government or donated by the LO.    aCTHDA

B.1      Valuation of plantation roads delineated in the ASP and paved with concrete, asphalt and/or macadam shall be equivalent to the sum of the value of land (VL) occupied by the road and its shoulders plus the value of the road pavement/improvement (VR).

Expressed in equation form:

Value of Plantation Road = VL + VR

Where:

         VL = Value of land occupied by the road and shoulders

         VR = Value of the road pavement/improvement

B.2      Valuation of roads delineated in the ASP and whose construction involved clearing, leveling/grading, earth-moving and filling of earth/coarse aggregate materials shall be equivalent to the sum of the value of land (VL) occupied by the road and its shoulders.

B.3      Value of Land (VL) shall be computed by using MVTD x 2 based on the unit market value (UMV) of the land most proximate/adjacent to it. If the plantation road traverses different land uses, the land with the lowest UMV productivity classification shall be used.    CTIEac

            However, in no case shall VL using the formula MVTD x 2 exceed the lowest computed value of a productive land within the estate.

B.4      If a plantation road deteriorates due to normal wear-and-tear or is partly or severely damaged by floods, erosion or any other natural calamities, the value of the road (VR) is determined as follows:

a.         Roads subject to normal wear-and-tear

The value of roads which are subject to normal wear-and-tear shall be computed using the "Cost Approach".

Expressed in equation form:

                                                    ERUL

Value of Road (VR) = RCN x  ———

                                                    EULN

Where:

            RCN = Reproduction Cost, New

            ERUL = Estimated Remaining Useful life 1

            EULN = Estimated Useful Life, New 1

If a road is subjected to regular repair and maintenance, its estimated remaining useful life (ERUL) may be enhanced and may even approximate its original economic life. Hence, a 15-year old road which has an original estimated useful life (i.e., EULN) of 20 years might still have 10 years of remaining useful life (ERUL), if properly maintained. The appraiser shall therefore exercise extreme objectivity in assessing the ERUL of roads covered by regular maintenance programs.

RCN may be determined by the Quantity Survey Method, i.e., itemized reconstruction of the bill of materials, or by any other method appropriate to determine its actual original value.

To ensure uniform implementation of this Guideline, a table showing the EULN of different types of roads and bridges is attached as Annex "A".

1.      In number of years

b.         Roads damaged by floods or erosion

Valuation of roads, which are partly or severely damaged due to floods or erosion or any other natural calamities, shall be determined by the following formula:    HICcSA

                                                                       ERUL

Value of Road (VR) = (RCN - RCNDP) x     ———

                                                                       EULN

Where:

            RCN = Reproduction Cost, New

            RCNDP = RCN of Damaged/Eroded Portion

            ERUL = Estimated Remaining Useful Life

            EULN = Estimated Useful Life, New

B.5      Trial routes, pathways or secondary roads, which involve only clearing and partial leveling of the area (i.e., no grading, earth-moving and filling of earth or coarse aggregate materials), that traverse productive land/s within the estate shall be valued as if the areas concerned are "deemed part" of the plantation i.e., valuation shall follow that of the land use/s traversed.

B.6      Bridges which are made of either concrete, steel, wood or combination of any of these materials shall be valued using the formula defined in Item III B.4.a. Bridges which are partially damaged shall also be valued in accordance with this Guideline. The value (MVTD x 2) of the land occupied by the approaches of the bridge shall have to be added to the value of the bridge structure. The final value of the bridge is therefore equivalent to:

Value of Bridge = VL + VB

Where:

            VL = value of land occupied by the bridge approaches

            VB = value of the bridge structure

IV.       REITERATION

The willingness of the seller (landowner) and buyer (farmers' group or farmers' cooperative) shall be necessary for the acquisition of roads and bridges. A farmers' collective agreement or Board Resolution executed by the farmers' group or cooperative, as the case may be, embodying therein their/its willingness to acquire the roads and bridges, shall be required.    cIADaC

V.        EFFECTIVITY

This Guideline shall take effect immediately.

All orders, circulars, rules and regulations inconsistent herewith are hereby revoke, amended, or modified as the case may be.

 

(signed) JESLI A. LAPUS

President & CEO

October 9, 1997

ANNEX "A"

ESTIMATED USEFUL LIFE, NEW (EULN) OF ROADS AND BRIDGES

 

                                                                                                     Years

A.     Plantation Roads

         Concrete                                                                               20

         Asphalt                                                                                  20

         Macadam                                                                               15

         Cleared/Leveled/Graded

                  And Filled with Earth

                  Coarse Aggregates                                                      n.a.*

B.     Bridges

         Concrete and Steel or Masonry — Large                            100

         Concrete and Steel or Masonry — Small                              75

         Steel — Heavy                                                                       50

         Steel — Light                                                                         40

Source: Data supplied by the LBPs Credit and Central Liability Department (CCLD).    DEcTIS

* EULN not applicable to this type of road.

 

LAND VALUATION GUIDELINE NO. 97-005

Series of 1997

SUBJECT:      LAND VALUATION GUIDELINE NO. 97-004, SERIES OF 1997, ON VALUATION OF ROAD AND BRIDGES

To ensure uniformity in the interpretation of Item II.B.B.3 of above subject, the following amendment is hereby issued:

FROM

Value of Land (VL) shall be computed by using MVTD x 2 based on the unit market value (UMV) of the land most proximate/adjacent to it. If the plantation road traverses different land uses, the land with lowest UMV productivity classification shall be used.

However, in no case shall VL using the formula MVTD x 2 exceed the lowest computed value of a productive land within the estate.

TO

Value of Land (VL) shall be computed by using MVTD x 2 based on the unit market value (UMV) of the land most proximate/adjacent to it. If the plantation road traverses different land uses, the land with the lowest UMV classification shall be used.

However, in no case shall VL using the formula MVTD x 2 exceed the lowest computed value of land traversed by the plantation road within the estate.

This Order takes effect immediately. 

  EDCIcH

(signed) JESUS F. DIAZ

Acting President

 



CONTACT INFORMATION

Department of Agrarian Reform
Elliptical Road, Diliman
Quezon City, Philippines
Tel. No.: (632) 928-7031 to 39

Copyright Information

All material contained in this site is copyrighted by the Department of Agrarian Reform unless otherwise specified. For the purposes of this demo, information are intended to show a representative example of a live site. All images and materials are the copyright of their respective owners.