January 10, 2003

 

JOINT DAR-LBP MEMORANDUM CIRCULAR NO. 03-03

 

AMENDING MEMORANDUM CIRCULAR NO. 26, SERIES OF 1996 AND MEMORANDUM CIRCULAR NO. 29, SERIES OF 1997 ON THE COMPOSITION OF CAP-PBD IMPLEMENTING STRUCTURES AT DIFFERENT LEVELS

 

I.          INTRODUCTION

The DAR and Land Bank of the Philippines through a Memorandum of Agreement signed on 09 September 1996 agreed to jointly implement the Credit Assistance Program for Program Beneficiaries Development (CAP-PBD). To effect its implementation, the DAR issued Memorandum Circular No. 26 series of 1996, prescribing the implementing Policies and Guidelines on the Availment of CAP-PBD on 25 October 1996. Correspondingly, the LBP issued Credit Group Memo Circular No. 97-001 containing the same guidelines on CAP-PBD fund availment.

However, certain provisions thereof need to be further revised in order to conform to the development brought about by the changes in the organizational structure both in DAR and LBP. These changes have brought concerns on the proper performance and discharge of functions and duties of personnel involved in the implementation of the Program.   CSAaDE

In response to this concern and to ensure the effective and efficient implementation of the Program at different levels, Article IV and V, item G of CAP-PBD MC No. 26, Series of 1996, Article II, 2.1-2.2 of MC No. 29, Series of 1997, and Article II, Item F of MC No. 07, Series of 1998, is hereby amended.

II.        REVISED COMPOSITION OF CAP-PBD IMPLEMENTATION STRUCTURES

 

The following committees shall have the following compositions and functions:

A.        National Project Management Committee (NPMC) 

  DAR Secretary : Chairperson

Executive Vice-President Agrarian and : Vice-Chairperson

Domestic Banking Sector, LBP


LBP Consultant : Member

First Vice-President (Coop Champion), LBP : Member

First Vice-President (Mindanao Group), LBP : Member

Undersecretary for Field Operations and : Member

Support Services, DAR


Undersecretary for Finance, Management : Member

and Administration


Assistant Secretary for Support Services : Member

Office, DAR


Branch Group Head (Where the loan proposal : Member

above P3M emanated)


Director, PARC Secretariat : Member

Representative, Farmer's Group : Member

The NPMC shall:

1.         Approve/disapprove projects for funding under the CAP-PBD, requiring loan assistance of more than Php 3 Million; and

2.         Decide on issues that need special attention on matters pertaining to policies and guidelines under the program.

B.        National Technical Review Committee (NTRC)

  Director, Bureau of Agrarian Reform : Chairperson

Beneficiaries Development, DAR


Assistant Vice-President, Program : Vice-Chairperson

Management Department, LBP


Assistant Vice-President, Development : Member

Assistance Department, LBP


Director, Finance Management : Member

Administration Service (FIMAS), DAR


Director, Project Development and : Member

Management Service (PDMS)
 

 The NTRC shall:

1.         Implement the policies approved by the NPMC;

2.         Prepare the checklist of necessary documents, including the required components of the feasibility study, for the proposed projects to be submitted by the proponent to the DAR/LANDBANK;

3.         Formulate the criteria and guidelines on the evaluation of project proposals subject to the approval of the NPMC;

4.         Validate/confirm project proposals approved by the Regional Project Management Committee (RPMC) and Provincial Project Management Committee (PPMC), prior to issuance of notice of fund transfer, as deemed necessary; and

5.         Review project proposals endorsed by the Regional Project Management Committee (RPMC) and Provincial Project Management Committee (PPMC) that need the approval of the NPMC, and recommend to NPMC approval of the proposals;

The technical staff of the Bureau of Agrarian Reform Beneficiaries Development (BARBD) shall act as the Program Secretariat to the NPMC and NTRC.

C.        Regional Project Management Committee (RPMC) 

  Regional Director, DAR : Chairperson

Regional Head, LBP : Vice-Chairperson

Development Assistance Center Head, LBP : Member

Regional CARPO for Support Services, DAR : Member

Regional Investment and Marketing : Member

Assistance Officer, DAR


Regional CAP-PBD Point Person : Member

Provincial Agrarian Reform Officer : Member

Concerned, DAR
 

The RPMC shall:

1.         Evaluate and approve/disapprove project proposals endorsed by the PPMC with loan requirements of not more than PhP3 Million (per proponent), and endorse those requiring loan assistance above PhP3 Million (per proponent) to the NPMC through the NTRC;

2.         Design and conduct institutional development interventions to address capacity building needs of CAP-PBD assisted organizations;

3.         Conduct monitoring and assessment activities and facilitate generation of reports on projects funded under the program; and

4.         Submit regular reports to NTRC through the Program Secretariat.

It is understood that all projects with financing requirements falling within the range for RPMC and NPMC approval have been pre-evaluated at the provincial level, initially approved and recommended by the PPMC for funding assistance.

The Regional Support Services Division (SSD) shall act as the program secretariat to the RPMC.

D.        Provincial Project Management Committee (PPMC) 

  Provincial Agrarian Reform Officer, DAR : Chairperson

Lending Center Head, LBP : Vice- Chairperson

Head, Development Assistance Center : Member

LBP


Chief Agrarian Reform Program Officer : Member

BDCD, DAR


Provincial Investment and Marketing : Member

Assistance Officer, DAR


Provincial CAP-PBD Point Person, DAR : Member

PARCCOM : Member

Municipal Agrarian Reform Officer (MARO) : Member

Concerned, DAR


Account Officer (concerned in relation to : Member

project under deliberation), LBP-LC
 

 The PPMC shall:

1.         Initially screen all project proposals and assess them with regard to proponent's eligibility and the project's technical and financial viability. In some cases, extend technical assistance to proponents in proposal preparation;   dctai

2.         Approve/disapprove project proposals requiring loan assistance of not more than PhP1 Million;

3.         Endorse project proposals requiring loan assistance of more than PhP1 Million to the RPMC;

4.         Design and conduct institutional development interventions to address capacity building needs of CAP-PBD assisted organizations;

5.         Conduct monitoring and assessment activities and facilitate generation of reports on projects funded under the program; and

6.         Submit status report to NTRC through the Program Secretariat, copy furnished the RPMC.

The Provincial Beneficiaries Development Coordinating Division (BDCD) shall act as the Program Secretariat to the PPMC.

 

III.       APPROVING LEVEL

Based on Land Bank's revised Codified Approving/Signing Authority (CASA), loan approval shall be undertaken by the Committees at the appropriate levels: 

  Loan Amount Approving Authority


(Per proponent)




PhP1M and below Provincial Project Management


Committee

Above PhP1M to PhP3M Regional Project Management


Committee

Above PhP3M National Project Management


Committee

 

All Orders, Memoranda, Circulars and Issuances inconsistent herewith are hereby amended or repealed accordingly.

This Memorandum Circular shall take effect immediately.   HIACac

Diliman, Quezon City, 10 January, 2003.

 

(SGD.) HERNANI A. BRAGANZA

Secretary, DAR                        

 

(SGD.) MARGARITO B. TEVES
President, LBP

 



CONTACT INFORMATION

Department of Agrarian Reform
Elliptical Road, Diliman
Quezon City, Philippines
Tel. No.: (632) 928-7031 to 39

Copyright Information

All material contained in this site is copyrighted by the Department of Agrarian Reform unless otherwise specified. For the purposes of this demo, information are intended to show a representative example of a live site. All images and materials are the copyright of their respective owners.